Most remodel plans reserve about 10 to 20 percent of the construction budget as contingency: toward 10 percent for a new, simple scope and toward 20 percent for a pre-1980 house or any work that opens walls and floors.

Choose the percentage

SituationStarting point
New-build or recent home, cosmetic scopeAbout 5 to 10 percent
Same-layout kitchen or bath in a 10 to 30-year-old homeAbout 10 to 15 percent
Pre-1980 home or layout changesAbout 15 to 20 percent
Structural work, additions, unknown historyAbout 20 percent or more

These are rules of thumb used in planning, not guarantees. A $41,300 mid-range kitchen in Chicago (model point) would reserve roughly $4,100 to $8,300 at 10 to 20 percent.

What contingency is for

  • Rot, mould or damaged framing found behind walls.
  • Outdated wiring that must be brought up to code.
  • Asbestos or lead-paint handling in older homes.
  • Subfloor repairs and leveling.
  • Permit corrections.

What it is not for

  • Upgrades you decide on mid-project.
  • Missing items from the original quote.
  • Furniture, decor and appliances not in the scope.

Rules for spending it

  1. Approve every draw in writing with cost and cause.
  2. Re-check the remaining reserve after each draw.
  3. If you use more than half before the midpoint, review the rest of the scope.
  4. Return unspent contingency to the budget at the end.

Keep planning

Frequently asked questions

Is 10 percent contingency enough?

For simple work in a newer home, often. Older homes and layout changes call for more.

Should contingency be included in the contractor’s price?

Usually it is your reserve, separate from the contract. Some contracts include a controlled allowance; read how it is handled.

Does contingency cover design changes?

No. Treat design changes as a separate decision with a written change order.

Plan this room in 3D

Percentages are planning heuristics, not financial advice.