A cosmetic kitchen refresh can finish in days to two weeks, a same-layout replacement usually takes several weeks on site, and a layout change commonly runs two to four months from design to final inspection once you include design, permits and cabinet lead times.

Planning timelines by scope

ScopeDesign and orderingOn-site workKitchen unusable
CosmeticDays to 2 weeksDays to 2 weeksA few days
Same layout, new cabinets and counters3 to 8 weeks (cabinet lead time)3 to 6 weeks3 to 6 weeks
Layout change with new services4 to 10 weeks (plans, permit, lead time)6 to 12 weeks6 to 12 weeks

What stretches the schedule

  • Custom cabinets and stone counters that must be templated after the cabinets are in.
  • Permit review and rough-in inspections on city calendars.
  • Hidden problems behind the walls.
  • Changing selections after the order is placed.
  • Appliance delivery gaps before the counter template.

How to protect the timeline

  1. Freeze the layout and finishes before demolition.
  2. Order long-lead items first and confirm dates in writing.
  3. Ask for a week-by-week schedule with the trade for each week.
  4. Set up a temporary kitchen with a microwave, kettle and a sink elsewhere.
  5. Keep a contingency of a couple of weeks.

Keep planning

Frequently asked questions

How long can you go without a kitchen?

In a same-layout remodel, plan for roughly three to six weeks without a full kitchen and longer with layout changes. A temporary setup makes it livable.

Why do cabinets take so long?

Semi-custom and custom cabinets are made to order, and lead times of several weeks are common. Confirm the current time with the supplier.

Does the timeline include permits?

Not on-site time. Permit review is a separate step that can add weeks depending on the authority.

Plan this room in 3D

Timelines are planning ranges, not promises. Ask your contractor for a written schedule.